Rebuilding WESH PCR1.

A rebuilt production control room combining virtualized Wheatstone and Sony controls with renewed workstations and room infrastructure.

Explore the build · 12 photographs ↓ · See the completed room ↓
Completed PCR1: finished control room with active monitoring
Completed PCR1: finished control room with active monitoring
My role

Led the PCR1 rebuild as WESH Director of Engineering, with responsibility for engineering, IT, facilities, and capital project delivery.

Project scope

  • Control-room and raised-floor infrastructure
  • Production workstations and technical integration
  • Virtualized Wheatstone and Sony hardware approach

PCR1 is the room on the left, separated from PCR2 by a doorway. Its rebuild used a virtualized Wheatstone and Sony hardware approach, distinct from PCR2’s physical hardware. This gallery follows the former room through removal, raised-floor work, equipment installation, and the completed control room.

Team recognition

2025 BeckTV recognition

The WESH PCR1 team received BeckTV’s 2025 award for Best Automated News Production Control during my tenure as Director of Engineering.

Project gallery

From the original room to the completed control room.

PCR1 before the rebuild: production control position and monitor wall
01 · BeforePCR1 before the rebuild: production control position and monitor wall
PCR1 before the rebuild: operator positions beside the doorway
02 · BeforePCR1 before the rebuild: operator positions beside the doorway
PCR1 before the rebuild: workstation displays and production monitoring
03 · BeforePCR1 before the rebuild: workstation displays and production monitoring
PCR1 before the rebuild: former audio console and adjacent equipment
04 · BeforePCR1 before the rebuild: former audio console and adjacent equipment
PCR1 with operator furniture removed and floor access exposed
05 · RemovalPCR1 with operator furniture removed and floor access exposed
PCR1 wall preparation and exposed floor infrastructure
06 · Room preparationPCR1 wall preparation and exposed floor infrastructure
Technicians working on the raised-floor support structure
07 · Raised-floor workTechnicians working on the raised-floor support structure
Floor panels staged beside the exposed supports
08 · Raised-floor workFloor panels staged beside the exposed supports
Ceiling services exposed during room and floor work
09 · InfrastructureCeiling services exposed during room and floor work
Equipment and materials staged in the refitted PCR1 room
10 · Equipment stagingEquipment and materials staged in the refitted PCR1 room
The result

The completed PCR1.

Completed PCR1: operator at the front production position
11 · Finished roomCompleted PCR1: operator at the front production position
Completed PCR1: finished control room with active monitoring
12 · Finished roomCompleted PCR1: finished control room with active monitoring
← All projectsNext: WESH · PCR2 →